![]() MBS-Austin, San Clemente #5
July,2009. "OJT" training in progress, building furrdowns Shown here is a good example of furrdowns being framed out all along perimiter of building. Columns frames between ext. windows, this pattern continues at 2nd level. Jose is our "OJT" certified coach working on web-tex scaffold, in training is Rosario Minero. Housekeeping was excellent. Light metal framing, 3-5/8" & 6" studs used for framing furrdowns. Framing layout 16",bracing spaced out every 4'. Eric Lumsden-foreman. Jobsite Safety inspection report excellent! Noe Vela/MBS-Training Coordinator |
|